Description
Material base data(25℃,60%RH)
Mixed material Data(25℃,60%RH)
Viscosity of mixed : 450MPaS
Mixing proportion (without aggregate):1.05
Mixed solids(with aggregate):85%
Potlife : 20min
Dry time:2hr
Walking Opening time: 8hr
Weight opening time: 48days
Operation time and temperature relation
Material physical properties after curing
Attention:
Construction prohibited when humidity is greater than 85%RH;
User's guidance:
After mixing, the material must be poured all over the floor and then scraped, so as to avoid the bottom of the aggregate and the poor surface effect;
Adopt the construction method of batch scraping firstly and then roller coating, and evenly collect the short wool or sponge roller;
Dosage strictly controlled in 0.08~0.1kg/m2, avoidaccumulation, otherwise foaming serious;
This material has very high requirements for construction. It must be trained by our company before use.
Storage:
Ideal storage conditions is 5-35 ℃ in cool and dry place, avoid sun exposure.